Yesterday, Harco Heavy Lifting has taken a new 4,300 m² production hall into operation at NorSea Business Park in Måde, Esbjerg. 

The handover takes place just short of one year after the agreement was signed and marks an important milestone in the collaboration between the two companies.

The new facility is the first step in an expansion that will increase Harco’s total Esbjerg footprint to 5,900 m² later this year.

The expansion is driven by strong growth and increasing demand for advanced lifting solutions in the wind industry.

The project has been developed in partnership with NorSea Denmark as part of strengthening NorSea Group’s position within wind energy. The building was delivered as a turnkey contract by KG Hansen & Sønner A/S and completed in 12 months.

At NorSea, the milestone supports the ambition to be a strong and reliable partner for the energy sector.

Office facilities are expected to be completed later in 2026.